Development Update - January 2023

January Milestones

New scopes will be starting in the month of January:

  • Excavation & Utilities at Building D – 1/4

  • Elevators B/FG – 1/3

  • Precast – 1/3

  • Exterior Metal Panels – 1/11

  • Elevator Storefronts – 1/9

  • Pool Building Glass Roof - 1/10

  • Heavy Timber Roof Structure at Chapel Building – 1/23

  • Foundation Walls - H1/H2 Villas

  • Retaining Walls - Villas

  • Utilities - J5/J6 Villas

  • Rough MEPs - Villas

  • Roof Dry-In/Install - Villas

  • Window Install - Villas

  • Foundation Waterproofing/Perimeter Drains - Villas


Construction progress aerial footage | December 2022


Trucking Impacts

  • Insulation & Drywall – Approximately 3 trucks per week*

  • Cabinets / Millwork – Approximately 4 trucks per week*

  • Flooring Material – Approximately 2 trucks per week*

  • Interior Doors & Trim – Approximately 3 trucks per week*

  • MEPF Material – Approximately 6 trucks per week*

  • Countertop Material – Approximately 1 truck per week*

  • Brick Veneer / Precast – Approximately 3 trucks per week*

  • Roofing Material – Approximately 1 truck per week*

  • Storefront / Glass Partitions – Approximately 1 truck per week*

  • Unit Appliances – Approximately 1 truck per week*

  • Balcony Railings – Approximately 2 truck per week*

  • Wood Framing Material – Approximately 3 trucks per week*

  • Irrigation/Landscaping Material – Approximately 3 trucks per week*

  • Underground Utility Material – Approximately 3 trucks per week*

  • Lumber delivery | Villas – approximately 2 trucks per week*

  • Rebar delivery | Villas – approximately 2 trucks*

  • Steel delivery | Villas – approximately 4-6 trucks*

  • Concrete Pour Dates*

    • Building – K (Pool)

- Walls and Floor – 1/26 - approximately 15 trucks*

- Pour 1, Slab on Grade Level 1 – 2/3 - approximately 15 trucks*

  • Building – B (Trellis)

- Slab on Grade Level 1 – 1/7 - approximately 2 trucks*

  • H1/H2 Villas

- Foundation walls – 1/11 - approximately 15-17 trucks*


Road Closures

  • 4th Street Work – 1/1/23

Public access will be closed beginning 1/1/23 and will re-open/close throughout the month. Access will be available to residences within the closed area throughout the duration of work.

- South of Maxwell to alley – closed 1/3 – 1/6 & 1/9 – 1/23

- North of Maxwell to alley – 1/1 – 1/16 & 1/18 – 1/23



4TH STREET WORK/ROAD CLOSURE UPDATE 1/13/23

  • New dates: Monday 1/16/23 through Wednesday 1/18/23. There is a small possibility of clean up work on Thursday.

    • The entrance to the jobsite will be shut down as will 4th Street on both sides of Maxwell. Revised traffic control plan below.

  • Water Shut Down: Tuesday 1/17/23, 8:00 am - 4:00 pm. Any building along 4th street between Maxwell and Mapleton will be without water during this time. All affected properties will receive notification from the public utility provider/contractor. The contractor will make every effort to turn water supply back on before the estimated restoration time of 4pm.