Development Update - September 2023

Writer's picture: 311 Mapleton Development 311 Mapleton Development

September Milestones

New scopes will be starting or continuing in the month of September:

  • Landscaping – All Month

  • Site Concrete (Sidewalks)

  • Site Retaining Walls – All Month

  • Site Fountain vertical finishes and testing

  • Asphalt – Paving of roadways has been pushed to September 13th – 16th

  • Pool equipment start up and testing

  • Elevator Install - J3-J4 / J5-J6 Villas

  • Exterior Flatwork - Villas

  • Flooring - J3-4 / J5-J6 Villas

  • Cabinetry Install - Villas

  • UG pluming - R5 Cottage

  • Concrete window well set - R5 Cottage

  • Backfill - R5 Cottage

  • Basement slab pour - R5 Cottage

  • Garage slab pour - R5 Cottage

  • Front Porch slab pour - R6/R7 Cottages

  • Truss install - R6 Cottage

  • Dry-in - R7 Cottage

  • Dry-in - R6 Cottage

  • Start rough HVAC - R6 Cottage

  • Start rough plumbing - R6 Cottage

  • Start siding - R6/R7 Cottages



Trucking Impacts

  • Rosch Retaining Wall Material – approximately 2 trucks per week*

  • Pool Tile & Finishes – approximately 1 truck per week*

  • Balcony Railings – approximately 1 truck per week*

  • Irrigation/Landscaping Material – approximately 4 trucks per week*

  • Drywall delivery – approximately 4 trucks per week*

  • Flooring delivery – approximately 2 trucks per week*

· Concrete Pour Dates

  • Villas - 9/12-9/15

Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.


Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles: