September Milestones
New scopes will be starting or continuing in the month of September:
Landscaping – All Month
Site Concrete (Sidewalks)
Site Retaining Walls – All Month
Site Fountain vertical finishes and testing
Asphalt – Paving of roadways has been pushed to September 13th – 16th
Pool equipment start up and testing
Elevator Install - J3-J4 / J5-J6 Villas
Exterior Flatwork - Villas
Flooring - J3-4 / J5-J6 Villas
Cabinetry Install - Villas
UG pluming - R5 Cottage
Concrete window well set - R5 Cottage
Backfill - R5 Cottage
Basement slab pour - R5 Cottage
Garage slab pour - R5 Cottage
Front Porch slab pour - R6/R7 Cottages
Truss install - R6 Cottage
Dry-in - R7 Cottage
Dry-in - R6 Cottage
Start rough HVAC - R6 Cottage
Start rough plumbing - R6 Cottage
Start siding - R6/R7 Cottages
Trucking Impacts
Rosch Retaining Wall Material – approximately 2 trucks per week*
Pool Tile & Finishes – approximately 1 truck per week*
Balcony Railings – approximately 1 truck per week*
Irrigation/Landscaping Material – approximately 4 trucks per week*
Drywall delivery – approximately 4 trucks per week*
Flooring delivery – approximately 2 trucks per week*
· Concrete Pour Dates
Villas - 9/12-9/15
Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.
Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads. Related truck routing articles: