Milestones

  • Large scale deck pours will continue throughout the month.


General Construction Activity

  • Underground Building Utilities

  • Concrete Foundations

  • Foundation Waterproofing

  • Backfill of Foundations


Trucking Impacts

  • Reinforcing Steel for Concrete – Approximately 1 truck per day*

  • Underground Utilities – Approximately 1-2 Trucks per week*

  • Concrete Pour Dates - Approximately 2-10 trucks per day unless noted otherwise

Large slab pour dates that will range from 40 to 80 delivery trucks:

  • Wednesday, 8/4/21*

  • Saturday, 8/7/21*

  • Tuesday, 8/10/21*

  • Wednesday, 8/11/21* Route Change to Alpine: There is construction unrelated to the 311 Mapleton project at 4th and Dellwood, and our concrete trucks cannot get through. We will be forced to route trucks to Alpine.

  • Tuesday, 8/17/21*

  • Wednesday, 8/18/21* Route Change to Alpine: 2nd instance of construction unrelated to the 311 Mapleton project on Dellwood, disabling our concrete trucks' ability to get through. We will be forced to route trucks to Alpine. It appears the work occurring on Dellwood may be on behalf of Xcel Energy.

  • Wednesday, 8/25/21*

  • Tuesday, 8/31/21*


Calendar view of construction activities, including estimated truck numbers linked here. Dates are subject to change pending weather/other real-world variables. If dates change, the original will have a strikethrough. The new date will be shown after and updated on the monthly development article + construction calendar. Thus far, changes have been minor in the overall scheme of things, and we'll continue putting our best efforts toward maintaining that goal.


Trucking impacts with the * asterisk are semi-truck-sized vehicles, or considered to be heavy impact deliveries, and are required to use the dedicated Dellwood and Alpine routes through the project's duration. All other vehicles will use the best available public roads.


Related truck routing articles:


UPDATES

  • Wednesday 8/11 | Trucking Impact

There is construction unrelated to the 311 Mapleton project at 4th and Dellwood, and our concrete trucks cannot get through. We will be forced to route trucks to Alpine.

  • Wednesday 8/18 | Trucking Impact

The second instance of construction unrelated to the 311 Mapleton project on Dellwood, disabling our concrete trucks' ability to get through. We will be forced to route trucks to Alpine. It appears the work occurring on Dellwood may be on behalf of Xcel Energy.